• the first 6 houses of the complex were built and fully inhabited;
• a functioning kindergarten has been built on the territory of the residential complex;
• finished adjacent territory (playground, recreation area, fountain);
• security system and video surveillance installed;
• the last seventh stage was built and commissioned. The following works are currently being carried out there:
- the installation of intercoms has been completed in the entrances of the house;
- 30% of tiling plinth and porches has been finished;
- fire-ventilation and electrical installation works have been completed in the underground parking lot;
- in the underground parking lot 80% of the additional storage rooms masonry is ready and 40% of entrance doors in the storage rooms installation is ready;
- the crushed stone preparation for figured elements of paving (tile) has been done on the adjacent area.