Herein we are talking about the current state of affairs at the construction site of the residential complex "Crystal Avenue" in Petropavlivska Borshchahivka.
In the second phase (11-A, Oksamytova St.) hall finishing, works on connecting electricity and gas supply networks, waterproofing works, landscaping of the territory are ongoing.
In the fourth phase (1, Kryshtaleva St.) the installation of the ventilated facade (85% complete), the installation of the wet facade (85% complete), the gasification of the building (60% complete) and the installation of fire equipment (90% complete) are ongoing.
In the fifth phase (1-B, Kryshtaleva St.) monolithic works on the 18th floor are being completed and bricklaying of the walls on the 10th floor is underway.