Construction of a new house in RC “Shchaslyvyi” at Yabluneva St., 11 is progressing in high gear. The builders are working strenuously to deliver the project prior to scheduled date, making sure that the quality of construction is not affected in any way. It’s commonly believed, that developers outside of Kyiv cut corners on the quality of construction, but in RC “Shchaslyvyi” we use the same materials and technologies as in expensive capital city districts. That’s why, if you’re looking for an apartment to buy, keep an eye on our projects, a new house is about to hit the market!
Between 4th and 7th sections of the building the works of installation of ceramic brick external walls and three-layer internal walls are being performed. We plan to complete these works by the end of March.
We continue assembling ventilation shafts, necessary for air circulation and creating comfortable climate in apartments. Plumbing system pipes are being now installed in these sections.
In sections 1–3 of the house the works of pouring solid-cast inter-floor covering on the ninth floor are being done. All in situ concrete works will be completed in the beginning of the next month. Simultaneously, we started installing external partition walls and internal walls.
RC “Shchaslyvyi” is 95% complete, 7 out of 8 houses are already occupied. The complex has improved beautiful territory and a security check point. Purchasing an apartment at Yabluneva St., 11 is the last chance to become a resident of a comfort-class complex in Sofiyivska Borshchagivka, and get your place of residence ready to move in. No constructions nearby, no dirty shoes. Beauty and comfort right at your door! Choose your future apartment before the market launch! Don’t hesitate to call us: (044) 499-2543 and (067) 663-8610. Sales Department: Sofiyivska Borshchagivka, Yabluneva St., 5-A.