CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2024)

25.12.2024

Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.

In the fourth phase (1, Kryshtaleva St.), lawn laying and tree planting have been completed. Preparations for commissioning are underway.

In the fifth stage (1–B, Kryshtaleva St.), the installation of internal gas supply systems, plastering and screed arrangement have been completed. Facade works (90% complete), interior finishing and electrical works, and elevator installation are underway. Apartment doors have been ordered.

In the last part of the underground parking lot, work on the insulation and waterproofing of the parking lot has begun.

You can find out details about the construction, terms of purchase of housing or promotional offers by calling: +380960230310.