We continue to talk about the progress of the construction of the residential complex "Crystal Avenue" in Petropavlivska Borshchahivka.

In the second phase (11-A, Oksamytova St.) work on connection of power supply networks and preparation for landscaping of the adj territory is going on. The arrangement of retaining walls and work on the paving of passages has been completed.

In the fourth phase (1, Kryshtaleva St.) the installation of the wet facade (98% ready), the gasification of the building (90% ready), and the improvement of the territory are in progress. The ventilated facade is completed. Cooling of cold transitions is installed. Finishing of public usage places (5% ready) and production of public usage doors has started. Preparation for stair railings installation is underway.

In the fifth phase (1-B, Kryshtaleva St.) bricklaying of the walls on the 13th and 18th floors and the roof is in progress. Installation of ventilation ducts is completed. Preparation for installation of windows is ongoing.

You can find out details about the construction, terms of purchasing housing or promotional offers by the phone: +380960230310.